Tick what you are doing and see which parts of the Building Regulations apply, who signs it off, and what paperwork you should end up holding.

Last updated July 2026 · built by working UK builders

Building regulations
What work are you doing?

Tick everything that applies — most projects trigger several.

Guidance for England and Wales. Scotland uses a building warrant system and Northern Ireland has its own regulations — the principles are similar, the process is not. Always confirm with your building control body before starting.

The parts of the Building Regulations, in plain English

PartCovers
AStructure — will it stand up, and stay up
BFire safety — escape routes, fire doors, alarms, spread of flame
CSite preparation and resistance to moisture — damp-proofing, ground conditions
ESound insulation between dwellings and rooms
FVentilation — extraction, trickle vents, air changes
GSanitation, hot water safety and water efficiency
HDrainage and waste disposal
JCombustion appliances and fuel storage — boilers, flues, stoves
KProtection from falling — stairs, ramps, guarding, glazing
LConservation of fuel and power — insulation, air tightness, efficiency
MAccess to and use of buildings
OOverheating in new dwellings
PElectrical safety in dwellings
SInfrastructure for electric vehicle charging

Three routes to approval

Full plans application

Drawings and structural calculations submitted and approved before work starts. Slower, but you get a decision notice, your builder has something specific to work to, and disputes on site become much rarer. The right choice for anything structural.

Building notice

No drawings — you give 48 hours' notice and the inspector checks as the work proceeds. Fine for small, well-understood jobs. Risky for anything complicated, because non-compliance is discovered after it has been built.

Competent person self-certification

A registered installer certifies their own work and notifies the council. Applies to electrics, gas, windows, insulation, solid fuel appliances and a few others. Verify registration on the scheme's own register — Gas Safe, NICEIC, NAPIT, FENSA, CERTASS, HETAS — rather than trusting a logo on a van.

The certificate is the point

Building regulations approval is not bureaucracy for its own sake. It is the paperwork that makes your work saleable. When you come to sell, the buyer's solicitor will ask for a completion certificate for every extension, loft conversion, structural opening, boiler, rewire and set of windows. Missing certificates mean an indemnity policy at best, a renegotiation at worst, and a stalled sale in the middle.

If you are buying rather than building, ask for those certificates at the viewing. Theviewing checklist has the full list.

Frequently asked questions

What building work needs building regulations approval?

Most structural work, extensions, loft and garage conversions, new bathrooms, drainage changes, replacement windows, boilers, heat pumps, electrical circuits and replacing more than 25% of a roof or a wall covering. Redecoration, replastering and like-for-like repairs generally do not.

What is the difference between a building notice and full plans?

A building notice is quick and needs no drawings — the inspector checks as you go. Full plans means submitting drawings and calculations for approval before you start, which takes longer but gives you certainty and a document your builder must work to. Full plans is the right choice for anything structural.

What is a competent person scheme?

Registered installers in schemes like NICEIC, NAPIT, Gas Safe, FENSA, CERTASS and HETAS can self-certify their own work as compliant and notify the council on your behalf. You receive a compliance certificate in the post. It is faster and cheaper than a building control application — but only if the installer is genuinely registered, which is worth checking on the scheme’s own website rather than taking their word.

What happens if work was done without building regulations approval?

It surfaces when you sell. The options are a regularisation application — which means opening the work up so the council can inspect it — or an indemnity policy, which covers the financial consequence without fixing anything. Lenders and buyers accept indemnity for older, minor breaches and are far less relaxed about structural work.

How much does building control cost?

For a domestic extension, typically £600–£1,200 including plan checking and inspections, whether you use the council or an approved inspector. Smaller jobs are less. It is a small fraction of the build cost and it is the document that makes your work saleable.

Viewing a property or putting in an offer?

Get a builder’s eyes on it first. We review listings, photos, surveys and reports so you know exactly what you’re walking into.

Get a builder’s property review — £59

Response within 24 hours · no-quibble money-back guarantee

Get a builder’s property review — £59